Rio Blanco County Road and Bridge Department

Road Conditions and Construction Advisories



For current weather conditions in Rio Blanco County and the surrounding area please check the National Weather Service website.


For more information on road construction and conditions around the State please go to the Colorado Department of Transportation website (CDOT).

The following major routes have "No Winter Maintenance" during the winter months. Winter activities such as snowmobiling are very popular along these roads:

    Road 8, North Fork from mile post 30.5 east to the county line.
    Road 17, Buford-New Castle from mile post 40.3 south to the county line.

We attempt opening these roads around Memorial Day, however the exact date depends upon winter snow and ice accumulations.

We have many other sections of roads in remote areas that are not plowed in the winter. If you have a question on a particular road, please call us at (970) 878-9590.


SPRING AND SUMMER 2008 CONSTRUCTION PROJECTS
PROJECT: LOCATION: DURATION:
Road Reconstruction CR 122 June 2 – August 9
Stabilization CR 8 @ Ripple Creek Pass June 9 – October 15
Chip Seal CR 5, Piceance Creek Rd July 7 – July 26
Highway Painting County-wide July 28 – August 23
Guardrail Installation CR 122 July 28 – August 30
Bridge Maintenance CR 32, Hauck Rd. August 17 – October 25


Back to the Road and Bridge main page.